How many scheduled hours are there for a 60-day project consisting of 8-hour days?

Prepare for the Virginia Class A Contractor License Exam. Review with flashcards and multiple choice questions. Utilize hints and explanations to master the exam material, ensuring you're ready to succeed!

Multiple Choice

How many scheduled hours are there for a 60-day project consisting of 8-hour days?

Explanation:
Total scheduled hours come from multiplying the number of days by the number of hours worked each day. For a 60-day project with 8-hour days, you multiply 60 by 8 to get 480 hours. This assumes every scheduled day is a full 8-hour workday and there are no holidays or overtime affecting the plan. The other numbers would require more hours per day or additional days beyond the given 8 hours per day.

Total scheduled hours come from multiplying the number of days by the number of hours worked each day. For a 60-day project with 8-hour days, you multiply 60 by 8 to get 480 hours. This assumes every scheduled day is a full 8-hour workday and there are no holidays or overtime affecting the plan. The other numbers would require more hours per day or additional days beyond the given 8 hours per day.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy